Boring machine ‘Lady Bird’ is almost done with its work digging under D.C.
Hat tip, DCist: This is Boring News: DC Water's 'Lady Bird' Completes Two-Year Mission
Boring machine Lady Bird is almost done with its work digging under D.C.
Transportation
By
Dana Hedgpeth and
Ashley Halsey III July 22 at 12:55 PM
A
massive machine called Lady Bird that is digging under Washington as part of a project to build a new sewer tunnel is expected to emerge this week from underground.
DC Water officials said Lady Bird a huge tunnel-boring machine that is longer than a football field and weighs 1,300 tons has dug 4½ miles underground over the last two years in the Anacostia River tunnel system. Crews were expected to bring the huge machine up to the surface Wednesday afternoon, using a special crane to carry it more than 100 feet through a vertical shaft, according to authorities.
But there was a delay in getting some handles welded on to part of the machine to help bring it up, so the effort was postponed by a day. Now crews are planning to pull it out Thursday, according to DC Water officials. ... When Lady Bird does emerge, authorities said it will be time for another boring machine to move in and dig as part of several different contracts on the $2.6 billion sewer project. ... Shes done, said John Lisle, a spokesman with the DC Water department.
....
Like most hip ladies in the city these days, Lady Bird has her own Twitter handle @LadyBirdTBM where it gives updates. ... On Tuesday, one of the posts read, if I see my shadow when I come out tomorrow, that means 6 more weeks of miserably hot, humid weather.
Meet Lucy, a 1,582-ton tunnel boring machine that tweets