Halfway through the longest build in history22 May 2009
Resumed construction has been under way at Watts Bar 2 for the last 18 months, but a visitor would find it hard to see much happening. Because construction of the plant was once abandoned, the current $2.49 billion project to turn it on by 2012 requires more assessment than actual building work. By Will Dalrymple
Construction of two 1200MWe Westinghouse PWR reactors at Watts Bar in southern Tennessee began in 1973, and carried on until 1985, when unit 1 was basically finished. That year, the Nuclear Regulatory Commission raised many questions that needed to be answered before unit 1 could be licensed (and it took another 11 years until the plant started commercial operation). Plant owner and operator Tennessee Valley Authority (TVA) created a plan to address these issues in 1985, but ceased construction on unit 2 at that time, having finished major structures, including pressure vessel, steam generators, pressurizer, turbines, condenser, generator and switchyard transformers, and having installed systems such as the reactor coolant piping.
In a 2007 letter to the NRC, TVA explained why it wanted to restart the project. It said that proceeding with the completion and operation of WBN Unit 2 is the best decision for TVA and the Tennessee Valley in terms of power supply, power price, generation mix, return on investment, use of existing assets, and avoidance of environmental impacts (by building new fossil-fuel plants, or siting new nuclear power stations elsewhere).
Although Watts Bar 2 is the first US nuclear construction project in almost 20 years, it is really closer to a restart than a new-build. In fact, TVA’s experience restarting Browns Ferry 1 in Alabama was a major influence. “With a rising demand for more baseload generation, TVA restarted Browns Ferry Nuclear unit 1 in June 2007, and the success of that recovery project helped us to understand what it would take to complete Watts Bar 2,” Ashok Bhatnagar, senior vice president of TVA’s nuclear generation development & construction, said recently.
Construction began on the three-reactor ...
http://www.neimagazine.com/story.asp?sc=2053037Interesting insight into the decisionmaking processes behind the nuts and bolts of nuclear power.
Among other points I was struck by the claim made by plant engineers when the project was shut down - that the plant was 90% complete. It turns out it was only 60% complete.
Honest mistake, difference of opinion or bait and switch?
Any way you look at it the conflict between the claims then and now are troubling.